top of page

Galleria Court

Lawtech worked closely with Harris Associates to ensure project success at Galleria Court in Peckham.

Galleria Court RTM Company Ltd

download.png

5.1m

May 2022 - March 2024

Key Facts

Galleria Court consists of a basement, ground floor and eight upper floors. There are 86 residential apartments along with artist studios. The height of the building is approximately 27 metres, with a habitable top story level. The property was fully occupied during the works. The lower ground floor consists of underground car parking, a plantroom and a bin Store. There were also gated courtyards located at the front and back of the building. 


Works comprised of the removal of the existing combustible cladding, and the design, supply, and installation of compliant external wall systems. This included:

  • Brickwork facades (retrofit fire cavity barriers)

  • Rendered elevations

  • Zinc cladding

  • Timber cladding

  • Aluminium spandrel panels

  • Roof terrace decking and balcony timber decking

  • Cavity barriers and fire breaks to all required locations to satisfy building regulations

  • Insulation where defective cladding was replaced to satisfy Building Regulations

  • All other replacement materials where the existing was removed due to combustibility i.e. substrates to cladding panels. 


Key Challenges:

  • Residents were notified in advance by the RLO with regard to works on their balconies, the roof terraces, and walkways. Access along walkways was closely monitored to ensure resident safety and prevent unauthorised access to the ongoing works.

  • Access to balconies was restricted during the removal and replacement of the timber decking. Protection was placed against balcony doors to ensure that residents (especially children and vulnerable people) were unable to access the balconies.

  • Materials were unloaded using a Hiab lorry upon delivery to site. They were then transported via trolley to either site storage or the specific areas where those materials were required that day. A goods hoist was used to raise materials to the required floor.

  • Deliveries were scheduled with a minimum of 48 hours’ notice, and were only authorised between the hours of 9am and 3pm. All deliveries were assisted by traffic marshals to ensure the safety of site staff, residents, and the general public.


Residents and local stakeholders received letters from our dedicated RLO updating them on the progression of the works. The Site Team received positive feedback from a number of residents throughout.

Project Gallery

bottom of page